Terminal commissioning started on November 26th 2017!

After successful completion of the Civil Defence safety inspection and the Fujairah Municipality inspections and documentation all terminals tanks were internally inspected for product receipt by third party inspectors on November 21st 2017 whereby all tanks were found to be suitable for receiving the first product.

The Gasoil transfer from a neighbouring terminal in the Port of Fujairah started on November 26th 2017 and was completed on November 28th 2017 successfully.
After a smooth internal terminal commissioning process and associated checks the terminal was ready for commercial operations on December 12th 2017.