Phase 2

Phase II of BPGIC Al-Fujairah Terminal consists of eight tanks with a total storage capacity of 601,600m³ which brings the total storage capacity of the terminal to 1,000,200m³. Phase II tanks are mainly designed for storing crude oil, whilst flexibility of storing Black products is also considered. Phase II tank configurations are four of capacity 107,700m³ each and four of capacity 42,700m³ each. Phase II shall also consists of building associated infrastructures including new pump manifold with high flow rate pumps meeting FOTT VLCC requirements, additional jetty lines, etc. Common infrastructure built under Phase I is already designed to cater for the Phase II utilities, fire fighting and power requirements. Completion of construction of Phase 2 is planned for Q4 2019.